Problems that often occur in the melamine production process

2011-08-15View Original

Thread Content

Please discuss the problems that tend to occur during the production of melamine. In some time, our design institute will need to design a plant capable of producing 60,000 tons of melamine per year, using the pressurized gas-phase quenching process. No relevant design has been done in the courtyard before, so there is a lack of experience. I hope everyone will ask as many questions as possible, as well as provide their opinions and suggestions. After all, many problems that arise in actual production are not entirely the operator’s fault; rather, they result from a lack of consideration for the actual manufacturing process during the design phase.
Reply #22011-08-15
I hope the original poster will go to the actual manufacturer to take a look and learn about the situation on the ground. That’s still better than the results of forum discussions.
Reply #32011-08-16
The main issues are clogging in the urea system, vibrations caused by uneven gas distribution in the fluidized bed, molten salt leakage, air leakage in the feeding legs, and a rapid increase in filter resistance
Reply #42011-08-16
Pressure method? Which technology is being used?
Reply #52011-08-16
Reply to 4# cthlj2007: I haven’t seen the process package yet, so I’m not quite sure
Reply #62011-10-18
Reply to 1# wslforever: Hello! Since your institution has no track record, there’s no problem in being fairly confident regarding the reliability of the technology and its maturity level. How does your technology compare to that of Yejing Company? Wish you success, as performance in the industry is crucial; once this design is finalized, business volume will be very high!
Reply #72011-10-20
Reply to 3# 83530255: So how do you solve the problem of clogging in your urea system? Is it due to clogged pipes or valves?
Reply #82011-10-20
Reply to 7# wow0011: Improve insulation and operate with care; the most important thing is to ensure proper feeding in order to prevent excessive cycle times, and no fresh urea should be added. We have had to discard some of the viscous urea in order to add fresh material. The process of cyanic acid and ammonia forming urea in the urea scrubber tower
Reply #92011-10-30
Dear expert 83530255: Besides the urea system, which other areas are prone to clogging?
Reply #102011-10-30
Reply to 9# lxq700918: Crystal pipes, hot gas coolers, etc
Reply #112012-02-04
How is your project designed at the moment? :lol

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.