Blowing of steam pipelines for the turbine at the freezing station

2011-08-29View Original

Thread Content

After purging the steam pipelines in the freezing stations, rust may form if they are left exposed for an extended period. How can this be avoided?
Reply #22011-08-30
Apply nitrogen protection, or keep steam flowing continuously.
Reply #32011-08-30
If the time is not too long, the amount of rust that forms will not pose a threat to the turbine; if the time is too long, it is possible to use nitrogen for protection!
Reply #42011-08-30
Once the steam purging is complete, single-unit testing should be carried out immediately

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.