Who has the risk assessment report for Class III pressure vessels?

2011-09-13View Original

Thread Content

Who has the risk assessment report for Class III pressure vessels? The requirements include aspects such as failure modes and risk control. Has anyone done this? Can you share it?
Reply #22011-09-13
This post was last edited by guanjian88 on 2011-9-13 16:05. 1. Basic design parameters of the pressure vessel being designed: pressure, temperature, material, medium, and external loads, etc; 2. Description of the main operating condition parameters ; . T$ C& U" Q9 I7 O0 M1 C 3: The designer should list all potential hazards that may occur under the design conditions, such as explosion, leakage, damage, deformation, etc ; 4. For failure modes that are already specified in the standard, refer to the relevant clauses of the standard ; 5. For failure modes and calculation methods not specified in the standards, explain the considerations regarding loads and the corresponding safety factors in the design ; 6. Properties of the medium, and measures for dealing with minor leaks, large-scale releases, and explosion situations ; 7. Determine appropriate personal protective equipment based on the potential risks to those around ; 8. Risk control involves not only failure modes during use, but also lifting, transportation, installation, operation, inspection, and maintenance during the construction process ;
Reply #32011-09-13
Risk refers to the presence of danger, that is, the potential losses that may occur; There is no risk if there is no danger. In risk assessment, risk consists of two components: one is the probability of a hazardous event occurring ; Second is, in the event of a danger, the severity of its consequences and the extent of the losses. The risk assessment system defines risk as the product of two independent terms—namely, the similarity of failure occurrences and the consequences of those failures. Risk inspection is a method that uses risk as the basis for determining the priority order of inspection procedures and managing them; it is a systematic tool that helps people make correct decisions regarding inspections and maintenance. At present, CNPC and Sinopec are vigorously implementing HSE management systems within their own organizations. The implementation of an HSE management system by enterprises represents a transformation in traditional safety management. Its fundamental purpose is to control risks, and its core tasks involve identifying hazards and achieving continuous improvement through process control. The procedure for conducting an HSE risk analysis is: 1 Hazard identification ; 2 Risk Identification ; 3 Risk Assessment ; 4 Countermeasures ; 5 Continuous improvement.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.