The drawings from the design institute were delivered today, and they don’t include a material list for things like cable trays and cables. Can we ask the design institute to add one?

2011-10-09View Original

Thread Content

The drawings from the design institute were delivered today, and they don’t include a material list for things like cable trays and cables. Can we ask the design institute to add one?
Reply #22011-10-09
I brought this up with our chief engineer, but the management didn’t give me a response.
Reply #32011-10-09
That is necessary. The design institute needs to provide you with the model, specifications, grade, route, height of the cable tray, as well as information on the suspension brackets, the depth and distance of the embedded suspension brackets, and the specifications and models of the cables, along with details regarding grounding...................
Reply #42011-10-09
There should also be an approximate quantity, etc.; this is necessary!
Reply #52011-10-09
What must be provided is the basis for the construction procurement plan.
Reply #62011-10-10
You need to consider the responsibilities and consequences; as long as you persevere, you will eventually get a satisfactory response
Reply #72011-10-10
When a design institute prepares design drawings, these elements should be included without any need for special mention; therefore, it is reasonable to request that the design institute provide them.
Reply #82012-04-20
Hello, may I ask about the model and quantity of cable trays indicated on the drawings? I know the width and elevation of the trays, but what do things like S05-1316*10 and S02-16F*33 mean?
Reply #92012-04-20
Some design firms choose products from certain manufacturers when working on projects, but the client may not understand the meaning of those product codes, leading to a lack of communication between the two parties
Reply #102012-04-20
We often encounter such situations as well; these days, many design firms are completely dishonest – once they get the money, they start offering discounts.
Reply #112012-04-21
After the design institute completes the material list, and the material supervisor of the construction unit has reviewed it, a reasonable procurement plan is formulated.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.