What is the relationship between foundation treatment, foundation testing, and pile foundation construction? Can they be carried out simultaneously?
We look forward to the guidance of professionals. Thank you
Foundation treatment: It involves modifying foundations that do not meet the required standards. Common methods include dynamic compaction, cement mixing piles, and CFG piles; for more details, refer to the \"Technical Code for Foundation Treatment in Buildings\" (JGJ 79—2002); Foundation testing: It involves assessing the bearing capacity of the foundation as well as other parameters; this depends mainly on the purpose of the testing ; Pile foundation construction: When the natural soil or soil that has been treated cannot meet the required bearing capacity, rigid piles must be designed in accordance with the design specifications. These include manually dug piles, high-strength concrete pipe piles and other precast piles, as well as bored cast-in-place piles. Generally, for the same building or structure, it is not advisable to use different types of pile foundations, or a combination of pile foundations and natural foundations; installing settlement joints will suffice.
This area has been processed and inspected; can construction begin on this site now? The deadline is a bit tight; can we carry them out simultaneously?
Reply to 4# dugutianzuo5: If the test results meet the design requirements, then the next processing step can be carried out.
Reply 5# moqichangqing: Is that okay? Are the test reports available immediately?
The official test report needs to be archived; as long as the test results meet the requirements, work can generally proceed to the next stage.