Thread Content
I am just getting started with LNG liquefaction plants. Could you provide information on the equipment, process flow, operating procedures, and other relevant details related to such plants? What are the mainstream equipment and processes used in the LNG liquefaction plants that have been built in China? Imported or domestic? Thank you first.
Not many are in operation domestically; the largest one at present is Kunlun Energy’s Guangyuan facility, with a capacity of 1 million cubic meters of LNG, commissioned in May last year. 1 was put into operation; the process is from the United States
Hehe~~~ Buddy, it seems your information isn’t very accurate! There are already LNG liquefaction plants in operation in the country, and there are many of them! The largest facilities at present are Guanghui’s LNG plant in Shanshan, with a production capacity of 150 cubic meters per day; CNOOC’s plant in Zhuhai has a capacity of 600,000 cubic meters per day; Dazhou Huixin’s plant has a capacity of 1 million cubic meters per day; and Ordos Xingxing Energy’s plant also has a capacity of 1 million cubic meters per day. All of these plants have been in operation for several years now! Huayou Guang’an and Guangyuan have not yet started operations; all the aforementioned projects utilize BV’s PRICO process. In China, there are currently nearly a hundred LNG plants that have been built, are under construction, or in the planning stage
It’s probably not easy to get this information, as it relates to trade secrets! There are many friends in Haichuanli who work in this field; you can learn more from them
The main equipment such as compressors are imported, while most of the rest are domestically produced
I was wondering: are there any companies in our country capable of carrying out LNG projects from start to finish? From what I’ve read in forums, it seems that the Ningxia cleaning project was carried out by Sichuan Air Separation, and it also seems that Chengdu Cryogenic does a great job as well~ :L It’s a bit difficult to tell the difference between Chengdu Cryogenic and Sichuan Air Separation~
Many people working in cryogenic engineering in Chengdu come from Sichuan Airlines. Both of these companies are capable of handling LNG turnkey projects; you can simply contact them by phone
This post was last edited by kun605 on 2012-4-4 23:27. The Huayou Guang’an LNG plant is already in the testing phase, but things are not going very smoothly
Guanghui uses Linde’s technology, not BV’s; BV’s technology is suitable for medium and small production volumes, while Linde’s technology works better with larger scales
The 600,000-ton domestic production project in Tai’an, Shandong is the largest of its kind to date; however, CNPC has even larger projects, and it is expected that both will begin operations around the same time
The main manufacturing processes are still Lind, Dessinib, and Conness; components that require ultra-low temperatures are mostly imported.