Dear sea friends, please share the ordering time for the instruments for new projects at your respective workplaces
Reply #22012-02-03
. . . With the ordering deadline set, everyone can start making contacts now
Reply #32012-02-03
For ordinary valves, the time is 2 to 3 months (domestic-made); The import process takes 8-12 weeks, with a longer duration of up to nearly 6 months. The instrument typically lasts 0.5–1.5 months (for domestic models) ; Imported, 8–12 weeks old
Reply #42012-02-03
Okay, thank you to both sea friends:handshake

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.