2012-02-07View Original

Thread Content

Our company has two sets of S-NPK devices with an annual output of 100,000 tons. Since they were put into operation, they have not reached the designed capacity. The main reason is that the equipment is prone to corrosion, which makes on-site management very difficult. At present, almost all valves and mixing paddles are changed to plastic or graphite. The pipes are basically PPH pipes. However, trunk equipment such as bucket elevators cannot be replaced by other materials. Maintenance is very difficult. Please help me, thank you!
Reply #22012-02-08
It is almost impossible to use the full designed capacity. It would be good if 50% can be used. Usually when the production capacity reaches 60%, it is necessary to expand the capacity.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.