Consultation on explosion-proof PLC cabinets

2012-03-27View Original

Thread Content

A project requires that the PLC cabinets be placed in the explosion-proof area on site; there are two such cabinets. Should I choose a fully sealed explosion-proof design or one with positive pressure ventilation for explosion protection? These are the only two options I know of. If it’s a fully sealed design, how can heat dissipation take place inside the cabinet? Could the experts please advise me on what to do? It would also be great if you could recommend some suitable cabinet manufacturers.
Reply #22012-03-27
Build a house similar to an analysis cabin, with positive pressure ventilation and explosion-proof air conditioning inside. The key is the explosion-proof certification for the cabin; find a qualified manufacturer to handle it.
Reply #32012-03-27
It’s too troublesome; just using a cabinet directly isn’t allowed either on-site
Reply #42012-03-27
You can consult Shanghai Institute of Automation Instruments SIPAI! For imported products, you can contact ROSE, KOOPER, or get in touch with me!
Reply #52012-03-27
In a case like the owner’s, it depends on the power level of the PLC system; if it is quite low, then an explosion-proof enclosure can be used. However, it is best to use a positive pressure ventilation type. Currently, in China, apart from Huarong, there are also several companies that do a good job in manufacturing positive-pressure cabinets. I have previously designed PLC control systems, and many of the expansion racks required positive pressure ventilation, so I am familiar with this.
Reply #62012-04-09
Several projects we have undertaken have used positive pressure ventilation to prevent explosions
Reply #72012-04-10
PLCs can be of the wide-temperature type and do not require cooling. The specific temperature depends on the parameters set by the PLC manufacturer; I know that Siemens 200 PLCs are available in such wide temperature ranges
Reply #82012-04-10
I have an AB 1756 series model; it needs cooling. Could someone with experience give me some advice?
Reply #92012-06-12
It must be said that regardless of the series of products used, heat dissipation is necessary; it is a requirement for electronic components to function properly. It just depends on how you design them!

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.