HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

Method for preparing as-built drawings of pressure vessels

2012-03-29View Original

Thread Content

This post was last edited by chun_ing on 2012-3-29 at 18:12. How is it possible to prepare the as-built drawings for pressure vessels? Neither the tolerance specifications nor 150 provide a clear method; they only give a general idea. I have a few questions: 1. According to the documents, \"as-built drawings should accurately reflect the actual condition of the product; any items that do not match the blueprints as per the inspections should be clearly marked or modified.\" If everything needs to be modified, then the amount of data involved will be quite large. For example, if the drawing indicates a pipe outlet height of 155, but the actual measurement is 154, does this also need to be corrected in the as-built drawings? 2. Our company’s as-built drawing stamp has two fields: “Revision” and “Review”. Who signs for the revisions, and who signs for the review? 3. As stated in Article 1, if all the inspection dimensions are modified on the blueprint, it will likely become quite messy; therefore, it is necessary to redraw the as-built drawings ; If it is necessary to redraw the as-built drawings, how should the title block be filled out? For example: Who should sign for design, drawing review, and approval? Also, who is supposed to draw the as-built drawings? Is it the inspector who designs the as-built drawings, or is it the design firm that creates them? If it is the inspector who draws it, then are the review and approval fields to be signed by the design institute? Another question is: how should the dates of design, review, and approval be written? Should it be the original blueprint date or the actual date? 4. If the as-built drawings are redrawn, how should the as-built stamp be filled in on the drawings? “Are the signatures on \"Modify\" and the \"Design\" in the redrawn blueprint from the same person?
Reply #22012-03-29
I’ll answer the first two questions. First question: Our company usually only modifies the overall dimensions of the equipment and the length of the cylinder; as long as everything is within the tolerances allowed by the standards, there are generally no issues; Second question: Our company is the producer of this set of materials (that is, responsible for the final compilation of the software-related documents), and the revisions are signed by us; the approval is signed by the quality assurance officer.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.