Let’s discuss which type of coke oven is currently the most stable in operation and the most cost-effective! ! !
Reply #22012-04-06
These days, most efforts are focused on producing coke; large coking plants are now using 7-meter coke ovens, whereas before they used 5.5-meter and over 4-meter ovens
Reply #32012-04-08
Currently, the 5.5-meter ramming and 6-meter top-loading coke ovens are operating stably. Those under 4.3 meters have been gradually phased out. Heating at the upper part of coke ovens with a height of over 6 meters is difficult to address. Secondly, in the case of tamped coke ovens, if the coal cakes are too high, the tamping is not effective and the rate of coal collapse increases.
Reply #42012-04-09
Currently, the ones that operate more stably are still the top-mounted coke ovens of version 4.3 and the 5.5-meter rammed coke ovens; of course, the 6-meter rammed coke ovens also perform well
Reply #52012-04-09
Where were your 6-meter ramming coke ovens designed? Was it designed by the Wuhan University of Science and Technology Design Institute?
Reply #62012-04-09
Well, for 6M ramming, Wukou University has currently set up one unit in Henan Zhonghong.
Reply #72012-04-09
Compared to top-mounted coke ovens, rammed coke ovens can make use of more weakly bonded coal, resulting in higher output and lower costs; however, they also have disadvantages such as frequent occurrences of coal and coke collapse, numerous factors that affect the production process, a low operating efficiency, and a relatively low temperature coefficient.
Reply #82012-04-10
The 6-meter ramming coke oven is currently being redesigned and developed by Wuhan University of Science and Technology; our company does not have one yet~~
Reply #92012-04-10
Agree with the opinion from the second floor. Those with a 6-meter top installation and 5.5 ramming achieve more stable operation.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.