Where to make the opening for a flow and temperature transmitter using an orifice plate?

2012-04-16View Original

Thread Content

When using an orifice plate to measure flow rate, the straight pipe section should be 10D upstream and 5D downstream. Where should the temperature transmitter be installed downstream? Can it be installed anywhere after the straight section downstream?
Reply #22012-04-16
After 5D, just find a suitable location.
Reply #32012-04-16
A straight pipe section after 5D is sufficient! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! ! !
Reply #42012-04-18
It’s specified in the design standards; it’s the GB standards. . . . . . . .
Reply #52012-04-18
5D is enough after that! But it can’t be too far back! It must be a straight pipe section!

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.