Commissioning of gas separation unit

2012-04-17View Original

Thread Content

When a gas separation unit is started up for the first time, is it necessary to carry out a water test run? If so, how should it be conducted? Does the reboiler at the bottom of the tower need to be heated? A reward of 10 points is given, thank you
Reply #22012-04-22
Of course, water interconnection is necessary; check the sealing of the devices as well as any dirt inside the flushing equipment, and inspect the operation of the pumps. For water interconnection, the equipment must be filled with water, and circulation is achieved using a return pump. Due to the high height of the propylene tower, the water inside the tower should be drained when the wind speed exceeds level 5 to ensure the safety of the installation. Also, the reboiler at the bottom of the tower does not need to have its temperature increased. At the beginning of operation of the unit, there is a large amount of slag and other debris inside it; pay attention to the sealing of the pumps, and also clean the pump inlet filters regularly
Reply #32012-05-06
Since it’s the first time driving, water transport is essential. One of the main purposes of water interconnection operations is to provide training, helping operators to become familiar with the plant processes and the operation of individual units. Secondly, water intermodal transport is a test for the mechanical, electrical, and instrumentation systems of new installations. Ensure the normal operation of the electromechanical and instrumentation systems after the device is fed. During the water interconnection process, it is necessary to keep the flow continuous as much as possible, so that all pumps can operate continuously (the testing period for these pumps seems to be 24–48 hours). In order to minimize waste of water used in this interconnection process, temporary pipelines may need to be added on site. It depends specifically on the processes in your site.
Reply #42012-05-07
Learn more* – it takes plenty of production experience to achieve optimal operating conditions!

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.