In a double-code network diagram, the correct term for “total float” is (  ).   A. The amount of flexibility available for this task, without affecting the total project duration. B. The amount of flexibility available for this task, without affecting the earliest start time of its subsequent tasks. C. The amount of flexibility available for this task, without affecting the earliest completion time of its subsequent tasks. D. The amount of flexibility available for this task, without affecting the latest start time of its subsequent tasks. Correct answer: A
Reply #22017-12-29
A. The flexible time available for this task, without affecting the total project duration

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.