This post was last edited by Sammy_Wang on 2015-7-18 at 16:45. From processing and production, through molding, quality inspection before leaving the factory, installation, to actual use, every step must be carried out correctly in order to ensure the efficiency and lifespan of lined pipes. Therefore, today we will focus on explaining: what precautions should be taken during the installation of lined pipes to ensure their proper operation? Pipe clamps must be used to secure the areas under stress, such as plastic-lined tees, elbows, valves, faucets, and various water distribution points ; Pipe clamps should be installed at the pipe fitting joints, and the distance between the pipe clamp and the pipe fitting must not exceed four times the diameter of the pipe. The distance between the lined pipe and the wall (smooth wall) should be 12~15 mm. When plastic-lined steel pipes for water supply pass through floor slabs, sleeves must be installed; these sleeves can be made of plastic ; Metal sleeves must be used when passing through the roof ; The casing should be 50~100 mm above the ground and roof, and strict waterproofing measures should be employed. Axial twisting of the pipeline during installation is strictly prohibited; forced correction shall not be applied when it passes through walls or floor slabs. When plastic-lined steel pipes for water supply are placed parallel to other pipes, a certain protective distance should be maintained; if the design does not specify otherwise, this clear distance should not be less than 10 mm. The above are some points to keep in mind when installing lined pipes. We hope this will be helpful to everyone when needed. If you have any further questions, feel free to call us at any time; we’ll be happy to assist you!
Reply #22015-07-18
1. During installation, the pipes must not be baked, cut, exposed to open flames, or welded. 2. Combine short and long lining-formed pipes in a reasonable manner. 3. Use loop flanges, elbows, and tees reasonably. 4. The screws on the flange require symmetric and even force distribution.
Reply #32015-07-19
Learned it*:P:P:P:P:lol:lol:lol:lol

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.