Let’s work on questions 08-20 from the 2015 First-Class Constructor Examination: multiple-choice questions on laws and regulations, questions 34-35

2015-10-17View Original

Thread Content

I’ve gathered some questions from this year’s First-Class Constructor exam, along with their answers. I’m sharing them here to boost everyone’s interest in participating. Instead of posting them all at once, I’ll provide five multiple-choice questions or one case study at a time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; the moderator will give a reward to those who give correct answers. ****************************************** 34. Which of the following statements regarding the transfer, renewal, and termination of the right to use land for construction is correct? A. When the right to use construction land is transferred, the buildings located on that land, as well as any attached facilities, must be disposed of together. B. The term specified for the use of construction land shall not exceed 50 years. C. When the term of use for construction land expires, it is automatically renewed. D. When the right to use construction land ceases to exist, the person holding that right must promptly go through the procedures for cancellation registration. 【Construction Project Laws – Answer】A 【Construction Project Laws – Explanation of Answers】This question deals with land ownership, the right to use construction land, and easements. The holder of the right to use construction land has the right to transfer, exchange, contribute as capital, donate, or mortgage such right, unless otherwise provided by law. When the holder of the right to use construction land transfers, exchanges, contributes as capital, donates, or mortgages such right, the following provisions shall be complied with: (1) The parties shall enter into a corresponding contract in writing. The term of use shall be agreed upon by the parties, but shall not exceed the remaining term of the right to use the land for construction purposes. (2) An application for change registration shall be submitted to the registration authority. (3) The buildings, structures, and ancillary facilities attached to the land shall be disposed of together. When the term of the right to use land for residential construction expires, it is automatically renewed. The renewal of the right to use land for non-residential purposes after its expiration shall be handled in accordance with legal provisions. Regarding the ownership of the houses and other immovable properties on that land, if there is an agreement, it shall be in accordance with that agreement ; In the absence of an agreement or where the agreement is unclear, matters shall be handled in accordance with the provisions of laws and administrative regulations. When the right to use land for construction ceases to exist, the transferor shall promptly handle the cancellation registration. The registration authority shall revoke the certificate of the right to use construction land. See page P21 of the textbook. 35. For special plans for sub-projects with a high degree of risk and exceeding a certain scale, an expert review meeting should be organized. A. Safety supervision and management agency B. Construction unit C. Project owner D. Supervision unit 【Engineering Regulations – Answer】 B 【Engineering Regulations – Answer Explanation】 This question concerns the regulations regarding the preparation of safety technical measures, special construction plans, and safety technical briefings. For special plans for sub-projects with high risks and exceeding a certain scale, the construction unit shall organize an expert review meeting. See page P229 of the textbook.
Reply #22015-10-17
34, A ---- 35, B
Reply #32015-10-17
34. Regarding the transfer, renewal, and termination of the right to use construction land, the correct statement is (A). A. When the right to use construction land is transferred, the buildings situated on that land, as well as any attached facilities, must be disposed of together. B. The term specified for the use of construction land shall not exceed 50 years. C. When the term of use for construction land expires, it is automatically renewed. D. When the right to use construction land ceases to exist, the person holding that right must promptly go through the procedures for cancellation of registration. 35. For special plans related to construction projects that are highly risky and exceed a certain scale, an expert review meeting should be organized. (B) A. Safety supervision and management agency B. Construction unit C. Project owner D. Supervision unit
Reply #42015-10-17
The statements regarding the transfer, renewal, and termination of the right to use construction land are correct. [A) A. When the right to use construction land is transferred, the buildings situated on that land, as well as any attached facilities, must be disposed of together. B. The term specified for the use of construction land shall not exceed 50 years. C. When the term of use for construction land expires, it is automatically renewed. D. When the right to use construction land ceases to exist, the person holding that right must promptly go through the procedures for cancellation registration. 35. For special plans related to construction projects that are particularly hazardous and exceed a certain scale, it is [B) who should organize expert review meetings.] A. Safety supervision and management agency B. Construction unit C. Project owner D. Supervision unit
Reply #52015-10-17
D. When the right to use land for construction ceases to exist, the holder of such right shall promptly go through the cancellation registration procedures
Reply #62015-10-17
34. Regarding the transfer, renewal, and termination of the right to use construction land, which statement is correct? A. When the right to use construction land is transferred, the buildings situated on that land, as well as any attached facilities, must be disposed of together. B. The term specified for the use of construction land shall not exceed 50 years. C. When the term of use for construction land expires, it is automatically renewed. D. When the right to use construction land ceases to exist, the person holding that right must promptly go through the procedures for cancellation of registration. 35. For special plans related to construction projects that are considered high-risk and exceed a certain scale, an expert review meeting should be organized. B. A safety supervision and management agency; B. The construction unit; C. The project owner; D. The supervision unit
Reply #72015-10-17
34. Regarding the transfer, renewal, and termination of the right to use construction land, which statement is correct? A. When the right to use construction land is transferred, the buildings attached to that land shall be disposed of together with the buildings and auxiliary facilities. 35. For special plans for construction tasks that are of a certain scale and pose significant risks, an expert review meeting should be organized. B. Construction unit
Reply #82015-10-17
34. Regarding the transfer, renewal, and termination of the right to use construction land, which statement is correct? A. When the right to use construction land is transferred, the buildings attached to that land shall be disposed of together with the buildings and auxiliary facilities
Reply #92015-10-17
34. Regarding the transfer, renewal, and termination of the right to use construction land, which statement is correct? A. When the right to use construction land is transferred, the buildings situated on that land, as well as any attached facilities, must be disposed of together. B. The term specified for the use of construction land shall not exceed 50 years. C. When the term of use for construction land expires, it is automatically renewed. D. When the right to use construction land ceases to exist, the person holding that right must promptly go through the procedures for cancellation of registration. 35. For special plans related to construction projects that are considered high-risk and exceed a certain scale, an expert review meeting should be organized. B. A safety supervision and management agency; B. The construction unit; C. The project owner; D. The supervision unit

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.