What tasks should be carried out on the level gauge before it is put into operation after a major overhaul?

2015-11-25View Original

Thread Content

What tasks should be carried out on the level gauge before it is put into operation after a major overhaul?
Reply #22015-11-25
1. Purging 2. Replacement with lean gas or N2 gas 3. Replacement with feed gas 4. After the synthesis tower is started up, check that all valves are in their normal operating positions 5. Once crude alcohol is produced, open the root valve and the self-regulating shut-off valve; use the self-regulating valve to make adjustments, and then open the valve for transporting the refined alcohol

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.