Is there such a pipeline design?

2017-05-24View Original

Thread Content

Is there such a pipeline design? The pipes before and after the air collection tank are both DN100, while the section in the middle, along with the valve, suddenly changes to DN150, leaving the designers completely confused.
Reply #22017-05-24
It’s really the first time I’ve seen it; I don’t know why
Reply #32017-05-24
Rare, kind of interesting; I’ll give it some thought
Reply #42017-05-24
It is possible to reduce the flow velocity by expanding the diameter; this 150-length pipeline is controlled by only one ball valve. By reducing the flow rate of the medium, the ball valve has a greater ability to regulate the passage of the medium
Reply #52017-05-24
I have indeed encountered situations where the client submitted a procurement plan as soon as the design drawings were ready. Later, changes were made to the process diagrams, but the client had already purchased the materials. At their insistence, a diameter change was added
Reply #62017-05-24
:lol:lol, this situation really does come up often
Reply #72017-05-24
As a supplementary note, my investment project is of the EPC type.
Reply #82017-05-24
Personally, I think that when the diameter increases, the flow velocity decreases; as a result, some of the liquid entrained in the flow is separated out and carried away through the pipes below. If the pipe diameter is the same, then the entrained liquid will basically not precipitate. Don’t ask me what happened; I don’t know either. :lol
Reply #92017-05-24
From the photos, a branch pipe is connected to the main pipe; a DN150 main pipe would also be reasonable. Perhaps during the initial design, the device’s connection port was specified as DN150, but the manufacturer manufactured it as DN100; since the pipe material had already been purchased, only the connection port was changed.
Reply #102017-05-24
It’s probably because there isn’t enough material; that’s how it’s installed. There’s not much point in designing it this way
Reply #112017-05-24
Some rotameters change the diameter of the tube – is that for buffering purposes? I don’t know

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.