Thread Content
Construction unit or manufacturing unit? If it belongs to the pressure vessel category, does the construction unit have construction qualifications?
The construction unit is usually responsible for the welding group when the tower is brought into the site in sections. If the tower is a pressure vessel, the construction unit needs to have corresponding construction qualifications and comply with relevant laws and regulations. The manufacturing unit is usually responsible for manufacturing various parts of the tower and conducting inspection and testing during manufacturing to ensure that it meets the design requirements. .
This should be decided by the owner, usually by the manufacturing unit.
This depends on the scope of the contract (purchase contract, installation contract). In most cases, this is done by the installation unit. The installation unit needs to have general contracting qualifications or mechanical and electrical installation qualifications.
This post was last edited by Wise Ming on 2023-4-9 15:54. On-site welding of segmented towers requires a large amount of tooling (such as: Platforms, roll-on tires, welding machines, and even welding rod warehouses), cranes, scaffolding, welders, general workers, etc., water, electricity and lighting coordination, etc. It is generally impossible for manufacturers to have such manufacturing conditions, so the installation unit is generally responsible.
:handshake:handshake thank you all
The owner has the final say and can give it to whoever he wants. Generally, it is better managed by the manufacturing unit, and the responsibilities for installation and construction must be clearly defined.
The question of who is responsible for the workload of the on-site assembly and welding of tower segments depends on who the workload is signed to when the contract is signed. It is still very clear. Whoever’s contract includes this workload will do it. If the pressure vessel is on-site segmented assembly welding, it must be done by a qualified construction unit. This part of the work needs to be reported to the local supervisory inspection department for inspection and notification.
Look at the scope of the subcontracting contract. If it is from a manufacturer, it should be done by the manufacturer if it is made in sections and transported to the site for assembly due to transportation reasons. If the contract requires segmented production and delivery, the construction unit should complete the assembly. The construction unit should have relevant pressure vessel qualifications.
Generally, the equipment manufacturer performs welding assembly on-site. It depends on how the contract is signed.