What needs to be done before CCCC? What after CCCC?
Reply #22018-12-27
Before handover, preparations for inspection and acceptance must be completed. Sinopec has specific requirements regarding the facilities at the time of handover, and after the handover, preparations for production begin
Reply #32018-12-27
Is it necessary to introduce a common medium before CCCC?
Reply #42018-12-27
The concept of transportation infrastructure needs to be clarified; in general, certain utility services need to be introduced in advance, such as water, wind, and electricity

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.