What are the stages of temperature control during the drying process of a newly built furnace?

2009-12-31View Original

Thread Content

What are the stages of temperature control during the drying process of a newly built furnace?
Reply #22009-12-31
0–150 degrees: Removal of free water from the lining; 150–350 degrees: Removal of crystalline water from the lining; 350 degrees and above: High-temperature sintering of the lining
Reply #32009-12-31
⑴150°C, remove free water; ⑵320°C, removal of crystalline water ; ⑶500°C, sintering of refractory materials. With the new type of refractory lining, newly built heating furnaces no longer require drying out.
Reply #42010-01-01
Although it is a new type of material that does not require baking, it is still best to undergo three stages of treatment
Reply #52010-01-01
Pay attention to the preparation of the pouring material during construction; it is preferable that it be thick and water-resistant. After the pouring material is prepared, it is best to allow natural ventilation for more than 10 days. In this way, there is basically no need to heat the furnace.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.