HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

【Daily Topic】【Civil Engineering Version 20170327】

2017-03-27View Original

Thread Content

Participation reward: 2 Wealth. Correct reward: 9 wealth. A earthwork excavation project commenced in January of a certain year; by the end of May of the same year, it was found that ACWP was equal to BCWS, and BCWP was less than ACWP. Then (  ).   A. Cost variance is zero. B. Cost variance is negative, indicating cost overruns. C. Schedule variance is zero. D. Schedule variance is negative, indicating schedule delays. E. Schedule performance index is zero. Reference: B D
Reply #22017-03-27
B. The cost variance is negative, indicating cost overruns   D. The schedule variance is negative, indicating schedule delays

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.