This post was last edited by hesonchang214 on 2017-5-1 08:29 Participation rewards: 2 wealth. the right reward: 6. When comparing the planned value and the actual value of the construction progress, if the progress target of the milestone event is used as the progress plan value, the actual value of the progress should be ( ). A. The actual progress of the overall schedule plan B. The actual progress of milestone events C. The actual progress of subsystems D. The actual progress of each sub-work Answer: B
Reply #22017-05-01
B. Actual progress of milestone events

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.