Participation reward: 2 Wealth. Correct reward: 6 wealth. A contract for the construction of a certain underground project stipulates that 80,000 m3 of earthwork is to be excavated in January, with a contract price of 85 yuan per m3. By the end of January, it was confirmed that 90,000 m3 of earthwork had been actually excavated, with a actual unit price of 72 yuan/m3; therefore, the cost variance (CV) for this project is ( ) ten thousand yuan.   A. 117 B. -117 C. 85 D. -85 Answer: A
Reply #22017-05-16
A contract for the construction of an underground project stipulated that 80,000 cubic meters of earthwork were to be excavated in January, with a contract price of 85 yuan per cubic meter. By the end of January, it was confirmed that 90,000 m3 of earthwork had been actually excavated, with an actual unit price of 72 yuan/m3; therefore, the cost variance (CV) for this project is (A) ten thousand yuan.   A. 117  B. -117  C. 85  D. -85

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.