I would like to ask those with experience: is it more effective to lay another layer on top of the existing SBS waterproofing layer to fix leaks, or is it better to remove it and redo the installation?
Reply #22017-10-18
Just lay a layer directly; it’s hard to work with it after removing it
Reply #32017-10-19
Generally, a layer is applied directly. Before laying the new one, first tidy up the old one
Reply #42017-10-23
It is recommended to remove the existing waterproof layer; laying it directly will increase the load. The SBS load in this province is not very high, but a leveling layer and a protective layer are required, so the load generally increases by around 40 kg per square meter.
Reply #52018-01-17
First of all, it’s best to level the base surface; if it’s not already level, it’s better to remove it. Additionally, if there is moisture between the existing waterproof layer and the base surface, this could cause bulging

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.