1. The project owner shall organize the project completion acceptance and preside over the acceptance meeting (the project owner should deliver a brief speech before the meeting, provide an introduction to the procedures for project completion acceptance, and give a summary speech at the end of the meeting). 2. The engineering survey, design, construction, and supervision units shall respectively report on the performance of their contractual obligations and on the compliance with laws, regulations, and mandatory engineering standards at various stages of project construction. 3. The acceptance team reviews the project documentation from the construction, surveying, design, construction, and supervision units. 4. The acceptance team and the professional team (comprising experts from the project owner, as well as those from survey, design, construction, supervision units, monitoring stations, and other relevant fields) conduct on-site inspections of the project quality. 5. The professional team and the acceptance team express their opinions, providing a comprehensive evaluation of aspects such as the quality of engineering survey, design, construction, equipment installation, as well as various management processes ; The acceptance team forms an opinion on the completion acceptance of the project, fills out the \"Construction Project Completion Acceptance Report\", and signs it (or affixes the official seal). C