For prefabricated prestressed concrete water tanks, a lifting plan must be prepared before lifting the prefabricated components. The elements that should be included in such a lifting plan are (  ).   A. Project overview B. Main technical measures C. Estimation of lifting costs D. Safety measures E. Measures for civilized construction Correct answer: ABDE
Reply #22018-01-10
ABDE ).   A. Project Overview B. Main Technical Measures C. Lifting Cost Estimation D. Safety Measures E. Civilized Construction Measures
Reply #32018-01-10
For prefabricated prestressed concrete water tanks, a lifting plan must be prepared before lifting the prefabricated components. The elements that should be included in such a lifting plan are (ABCD).   A. Project Overview B. Main Technical Measures C. Lifting Cost Estimation D. Safety Measures E. Civilized Construction Measures

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.