2018-01-21View Original

Thread Content

The overall organizer of construction project management (the project owner or the project management company acting on its behalf) and the various parties involved in carrying out the project tasks each plan different levels and scopes of the quality control system for the construction project; this is done in accordance with the (  ) principle for establishing such a quality control system.   A. The principle of hierarchical planning B. The principle of decomposing overall objectives C. The principle of quality responsibility systems D. The principle of system effectiveness Correct answer: A
Reply #22018-01-21
Answer: A, the principle of hierarchical planning
Reply #32018-01-21
 B. Principles for decomposing the overall goal

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.