In an engineering network plan, the free float of a task refers to the amount of time flexibility available for that task without affecting ( ). A. The earliest start time of the immediate successor task B. The latest start time of the immediate successor task C. The latest completion time of the immediate successor task D. The completion time of this task Answer: A
Reply #22019-01-30
A、Earliest start time of the immediate subsequent task
Reply #32019-01-31
A、Earliest start time of the immediate subsequent task
Reply #42019-01-31
C、Latest completion time of the immediate subsequent task

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.