【Daily Question】Utilities – Civil Engineering – 20190824

2019-08-24View Original

Thread Content

This post was last edited by hesonchang214 on 2019-8-26 at 12:22. The flow rhythm refers to the duration of work for a professional team (  ). A、the total duration of all work B、the duration of work in one construction section C、the shortest possible duration of work D、the time interval between moving on to the next construction section. 【Answer】B
Reply #22019-08-24
 B、Duration on a single construction section
Reply #32019-08-24
D、Interval time before moving on to the next construction section
Reply #42019-08-24
B、Duration on a single construction section

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.