Question: What is the approximate delivery time for the high-pressure pump in the gasifier of an LNG receiving station, as well as the BOG compressor?

2018-03-18View Original

Thread Content

Question: What is the approximate delivery time for the high-pressure pump in the gasifier of an LNG receiving station, as well as the BOG compressor?
Reply #22018-03-18
It mainly depends on the different delivery times of various manufacturers. For example, with the BOG compressors from Bengbu United that I used before, it took about 3-4 months from signing the contract to receipt of the goods. Of course, this also depends on the size of the compressor you need
Reply #32018-04-03
High-pressure pumps are generally imported, with a delivery time of around 12 months. If the BOG compressor is imported, it also takes 8-10 months.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.