How should the welding coefficient for the end cap be determined? Should it be 1 or 0.85?
Reply #22018-06-05
1.0 still requires 100% PT-I
Reply #32018-06-21
Generally, it is the same as the welds of types A and B for the main structure; however, when the value for the main structure is 0.85, the welds on the end caps, which are formed after the panels are assembled together, also need to undergo 100% radiographic or ultrasonic inspection, with the acceptance standard being the same as that for the main structure.
Reply #42018-08-03
This generally depends on the design requirements. In my opinion, if 1,100% RT is to be achieved, it must be Grade II
Reply #52018-08-03
GB150.4-2011 specifies specific requirements; a coefficient of 1 means 100% RT is required. If it’s not necessary to carry out 100% RT, then that step can be omitted, as the cost of performing such inspections is very high. The standard requires 100% RT, so inspections must be conducted at 100%. If the standard does not require it, then we choose a coefficient of 0.85. . .

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.