For the simulation of a diesel hydrodesulfurization fractionation tower, is it necessary to specify the condenser temperature?

2021-08-24View Original

Thread Content

As the title suggests, during device production, the outlet temperature of the condenser at the top of the control tower is around 40 degrees. Should this design specification be included in the simulation?
Reply #22021-08-25
Set the temperature in the tower top condenser
Reply #32021-08-25
However, there is a problem of a large discrepancy between the set temperature of the condenser and the calculated value; how should this be addressed?
Reply #42021-09-29
Just provide one design specification, which is the top temperature of the tower, with the heat load as the variable.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.