How is the elevation of the equipment support points determined in chemical plant layout drawings? Is the thickness of the secondary grouting included?

2022-05-02View Original

Thread Content

How is the elevation of the equipment support points determined in chemical plant layout drawings? Is the thickness of the secondary grouting included? Is the elevation of the support point for the equipment in the diagram EL0.150 or EL0.200?
Reply #22022-06-13
It is not possible to determine the elevation of the support points from this diagram alone. Secondary grouting is carried out after the equipment has been installed, with the aim of improving aesthetics and preventing the equipment from loosening; based on this, the elevation of the support points should be 0.15 meters.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.