Who is responsible for designing the layout of the main reactor equipment in the process? ?

2017-12-13View Original

Thread Content

The technology suppliers, together with the construction party, requested the design institute to develop a equipment layout plan. Although many of the technology suppliers have existing production facilities of similar type, the construction party’s factory space is relatively small, so it is not possible to simply apply those existing designs. The design institute prepared a plan, which was criticized by the technical supplier, who said that it was not feasible at all. However, someone pointed out that the equipment layout plan (especially that of the main reactor) should be provided by the technical supplier; the supplier has an obligation to redesign the equipment layout based on the existing factory premises of the client. Otherwise, the technical solutions he provides would be incomplete. The design institute then refines the plan using the layout provided by the technical supplier. Now that the technical supplier refuses to provide such a plan, the design institute has to carry out the work itself, and when something goes wrong, they are asked why they don’t come to the site to take a look. There are many similar operating facilities, and the client doesn’t have much knowledge in this area. The question is: who is actually responsible for developing the equipment layout plan, and is there any basis for this decision? Can the design institute then accuse the technical supplier of inaction in front of the project owner?
Reply #22017-12-13
In a harmonious society, coordination is very important! The three parties need to agree on a plan, communicate together, and ensure the successful implementation of the project!
Reply #32017-12-13
In addition to providing PID, PFD, process specifications, equipment lists, and design data, technology suppliers must also supply preliminary layout drawings, which serve as a basis for design institutes to carry out the engineering design. The equipment layout diagram for the partition is prepared by the design institute.
Reply #42017-12-13
If looking for a basis, reference can be made to the provisions in SHSG-052 – Process Design Package for Petrochemical Plants. It’s on the forum.
Reply #52017-12-13
That’s true, but whoever is responsible should do it themselves; others can provide assistance, but if they take over the task, mistakes will be made, right?
Reply #62017-12-13
:Lol, when I met the people from our company’s design department, that manufacturer deserves to be beaten. We like to respect people, but no blaming; if something is truly wrong, a reminder is fine.
Reply #72017-12-13
I have this too, but there are two points I can rely on: 1. The project is by no means a petrochemical facility, and they won’t take that into consideration. . 2. This is a process package; they say I will only provide the technology, and that doesn’t count as a process package. .
Reply #82017-12-13
Please advise: should the equipment layout plan be provided by the technical supplier?
Reply #92017-12-13
:D took a look at your situation. You can consider the design institute, the equipment manufacturer, and your own company. The three parties should sit down and talk. According to the rules, it should be the manufacturer’s own technical team.
Reply #102017-12-13
Is your company’s technology department made up of fascists or gangsters? ? ? ;P;P
Reply #112017-12-13
People from our design department once had arguments with the client and our company’s own production workshop. That’s really amazing. But the design department is in the right.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.