2019-03-19View Original

Thread Content

Our company’s 2*55-hole, 6-meter top-mounted coke ovens were taken out of service in August 2016. The furnace body and related protective equipment have recently been overhauled, and we plan to carry out furnace drying. What are the differences and precautions between drying a cold furnace and drying a newly built coke oven? Please advise!
Reply #22019-03-19
It would be better to build a new oven, but the current content of crystalline water is likely low, so the heating period can be shorter

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.