What tests need to be conducted after a 10KV medium-voltage substation is built?

2025-07-21View Original

Thread Content

For the new project at the factory, the installation of high-voltage circuit breaker cabinets, parallel connection cabinets, incoming line cabinets, metering cabinets, control cabinets, etc. in the 10KV substation has been completed. What tests need to be carried out before handing over the facility? Is it usually done by the construction company, or by the supplier of the switchgear (Schneider)? Do these cabinets need to undergo factory testing at the supplier’s site (Schneider Integrated) before being installed on-site? I have no prior experience with new electrical projects.
Reply #22025-07-26
The construction unit is required to go through the approval process at the power supply company to obtain permission for power supply.
Reply #32025-08-31
Before leaving the factory, the cabinets are definitely subjected to corresponding factory tests, and relevant factory qualification reports are provided as a basis for delivery and equipment acceptance. After on-site installation is completed, handover tests are required, including voltage resistance tests and transmission tests, all of which are the responsibility of the construction party, who entrusts qualified organizations to carry them out. If higher-level authorities are involved in drawing power from the grid, stricter requirements apply, and relevant approvals from the appropriate departments are also needed.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.