[Engineering Version] Daily Question 20171220
Thread Content
Which of the following statements regarding the \"Special Provisions\" of the general contract for construction projects is correct? ( ) A. The interpretation of the \"Special Clauses\" for construction projects has the same validity as that of the \"General Clauses\".B. The interpretation of the \"Special Clauses\" for construction projects takes precedence over that of the \"General Clauses\".
C. The interpretation of the \"General Clauses\" for construction projects takes precedence over that of the \"Special Clauses\".
D. The \"Special Clauses\" and the \"General Clauses\" are complementary to each other.
E. The specific contents of the \"Special Clauses\" are determined through negotiations between the employer and the contractor regarding the specific requirements of the project, and these are then included in the contract text.
Correct answers: BDE