The existing Class A tank farm plans to add another 100-cubic-meter storage tank; the location for it has been reserved in advance. It does not constitute a major hazard source, and there are no design drawings available. Does this newly added storage tank require redesign, as well as the completion of all necessary procedures such as safety assessments, environmental impact assessments, and energy assessments? Please offer some guidance from those who are more experienced
Work on a project that includes the tank area; the project just needs to cover these storage tanks
First of all, thank you. A new company is about to apply for a work safety license, and this storage tank was not included in the initial design. Now there is concern that installing this tank might affect the approval of the work safety license; if procedures need to be added, what would those be?
It’s better not to install it; otherwise, experts might notice it when they inspect the site, which could affect the production license, and that license is very important. This supplementary procedure must be carried out within the project, as part of the three simultaneities requirement for projects.
Do you mean to obtain the license first and then go through the procedures to replenish the tank later?
Of course, evidence is what matters most
Hello, in this case, a design change can be made, and it will not affect the acceptance process