【Thorough Discussion on Maintenance Work in Haichuan】The \"Three Transparency\" maintenance approach proposed by a certain refining and chemical company – what are everyone’s thoughts on it?

2017-11-28View Original

Thread Content

I saw in the news that a certain refining company proposed a \"Three Brights\" maintenance approach – what are your thoughts on it? ——–--------------------------------- This November, the aromatic compounds processing unit at XX Refining and Chemicals underwent its first major maintenance campaign. Given the heavy workload and high intensity of this task, as well as the fact that most employees were participating in such a large-scale maintenance effort for the first time, the company’s Aromatic Compounds Department took a comprehensive approach, implementing the “Three Transparencies” method: transparency regarding the workload, transparency regarding the responsible persons, and transparency regarding the progress of the work, thereby ensuring that the maintenance tasks were carried out in an orderly manner. First, clarify the workload. Before shutting down for maintenance, the Aromatics Department conducts simulations for each phase of shutdown, maintenance, and restart, so as to have a clear understanding of the overall workload during the maintenance period. Adjust the work teams as appropriate based on the workload at each stage to optimize personnel allocation. During the shutdown period, tasks were relatively concentrated, so the department merged the four shifts into two larger shifts; four shift leaders took turns serving as the main and deputy supervisors of these larger shifts, adopting a two-shift rotation system. The team established several shutdown teams led by key members, assigning specific tasks based on each team’s specialized skills, so that everyone could focus on their area of expertise. Each group and each class presents their daily workload at the daily meeting, summarizes the achievements promptly, identifies problems, and then works together to come up with solutions to those problems. Second, identify the person responsible for the work. In addition to the tasks assigned uniformly by the department, the four teams are responsible for specific areas within the plant; each team leader acts as the person in charge of that area. The work responsibilities of these team leaders are supervised and guided by the unit managers in terms of safety, process, and equipment aspects ; The team selects skilled operators with extensive work experience and a strong sense of responsibility to serve as group leaders, clearly defining their responsibilities and powers; the work of each group is inspected, supervised, and verified by the team leader. The work responsibilities of team members, shift leaders, and unit managers are visualized and structured in a grid format; for special tasks, confirmation and signatures from the operator, shift leader, and manager are required to ensure closed-loop management. Third, clarify the work progress. The inspection, repair, and modification of equipment is a systematic project; if any step in this process is not properly managed, it can affect the overall progress. To this end, each team further refines the network diagram showing the shutdown of the facility; they list on the wall the names of the tasks related to maintenance, construction, and renovation, the duration required for these tasks, the HSE requirements, the contractors involved, and the persons in charge. They evaluate and compare one another’s work, making it clear at a glance how much time is needed for each type of task. Before the daily shift change, the progress of tasks completed that day is recorded in charts, allowing teams to stay informed about the progress of work in their respective areas and thus ensuring the overall schedule for maintaining the facility. To date, aside from the p-xylene unit which is still under shutdown for purging, units such as aromatic extraction and isomerization have been successfully handed over for maintenance, with all operations completed ahead of the originally scheduled deadlines.
Reply #22017-11-28
If implemented strictly, the \"three disclosures\" can help improve the progress and quality of maintenance work.
Reply #32017-11-28
The Three-Lightwork Method seems pretty good; it depends on how one views and applies it.
Reply #42017-11-28
The key to the Sanliang working method is openness and transparency; it ensures that not only those involved are aware, but others as well, which facilitates supervision and inspection, and also allows employees with specialized skills to utilize their expertise. If implemented strictly, it should be a good approach.
Reply #52019-12-19
If implemented strictly, it should be a good approach.
Reply #62020-02-08
It’s a good approach; it helps to train the team and improve the pace and quality of work interruptions
Reply #72020-03-14
These are all summaries of established companies, and they are all very good. According to our company’s approach, we first list the maintenance tasks; then, using P6 software and taking into account the maintenance time and the contractor’s workforce, we calculate everything to manage the critical path. The workshop is divided into areas; in other words, the maintenance area is split into 4 sections, each to be managed by a separate team, with other day-shift staff providing support and coordination. Meetings are held every morning and afternoon to keep things on track. Thanks to the support of P6 software, the maintenance progress is very clear and easy to understand at a glance. I think that for large-scale enterprises, it is essential to use advanced tools. Nowadays, devices are becoming larger, and the workforce is gradually being reduced; the era of constant human supervision is over.
Reply #82020-03-15
Engineering management software allows for greater detail, and it enables the inclusion of resources and manpower. It helps identify the critical path, and the entire process can be continuously recorded
Reply #92022-08-25
The Sanliang working method is very suitable for assigning tasks in workshops; it’s worth learning!*

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.