Why must steam pipeline purging be carried out after the insulation work on the pipeline system is completed? Thank you!
Reply #22015-07-09
To reduce heat loss and save steam. It is also to prevent people from getting scalded by the pipes.
Reply #32015-08-09
It seems that this is mentioned in the pipeline standards, but not all parties necessarily follow it; see http://bbs.hcbbs.com/thread-1067630-2-1.html

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.