A coal-to-natural gas project is planned to be built; now that a preliminary organization needs to be established, what departments should be set up and what are their responsibilities? Thank you!
Civil engineering, process technology, equipment and instrumentation, material supply, on-site assembly, safety and environment
Thank you! Currently, only preliminary preparations are being made; the organization may not yet need such detail.
The main thing is to form a project team; key specialties such as process engineering, equipment, electrical systems, instrumentation, structure, and water supply and drainage still need to be represented.
The Office for Approval and Permitting, the Comprehensive Logistics and Administration Office, and the Finance Department are sufficient.
Could you provide an update on the progress? Is it possible to reveal information about the site where the project is planned to be built? Hiring?
In the initial stage, all that is needed is an administrative and logistics coordination office (which is responsible for overall leadership: external coordination, including the approval process for preliminary feasibility studies, process packages, as well as assessments related to energy use, environmental impact, and safety; design, and manufacturing supervision); Internal department coordination) ; There should also be a technical department; people who understand technology and equipment are needed, and it’s best to have two dedicated supervisors in charge ; Finally, we need someone from the engineering department with some experience in project construction supervision and installation. These three departments are sufficient in the initial stage; subsequent departments can be detailed later
To establish the preliminary organizational structure, a preliminary working group composed of professionals from areas such as administration, human resources, logistics, finance, safety, process engineering, equipment, civil engineering, instrumentation, and electrical engineering should be formed. In the case of a turnkey contract, these professionals should be able to handle the preliminary feasibility studies, negotiations regarding the process packages, and the basic design phases without any issues.
The proposed natural gas project is currently in a very early stage. It is of course the evaluation phase for accurate project forecasting, fundraising, site selection, etc. First, communicate with the design firm to understand the general situation, and then establish a project team based on one’s own actual conditions; this team should have capabilities in coal-to-gas production processes, finance, and public relations. In the initial stage, the focus is on pursuing projects and conducting negotiations. As the project progresses, your understanding also improves, and you gradually assemble various types of talent.
You are the owners, not the design firm. General Manager – several vice presidents – Technical Department, Engineering Department, Procurement Department, Finance Department, Human Resources Department, Administration Department.