Everyone, work on question 48-2015 from the First-Class Constructor Examination’s \"Project Management\" section – answers to questions 17-18 will be rewarded if correct

2015-11-06View Original

Thread Content

Those who come to do exercises every day are the eager learners among our users! ! Today marks the start of the project management series – welcome to join! http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png http://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.pnghttp://bbs.hcbbs.com/static/image/hrline/line7.png Some exam questions from this year’s first-level constructor examination have been collected, along with their answers. I’m sharing them here to encourage more people to participate. Instead of posting all of them at once, a few multiple-choice questions or one case study will be presented each time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; the moderator will give rewards for correct answers. ****************************************** 17. It is known that project AF has two parallel tasks, G and H. The latest start time for task G is day 12, while its earliest start time is day 8. For task H, the latest completion time is day 14, and its earliest completion time is day 12. The time intervals between task F and tasks G and H are 4 days and 5 days respectively. What is the total float for task F? A. 0 B. 5 C. 7 D. 9. Answer: C 18. Regarding construction budgets and the comparison between the budget based on construction drawings and other types of budgets, which statement is correct? A. The construction budget is prepared using budget quotas, whereas the budget based on construction drawings is prepared using construction quotas. B. Methods for comparing these two types of budgets include a physical comparison method. C. Under normal circumstances, the amount of labor required and the labor costs in the budget based on construction drawings are lower than those in the construction budget. D. Under normal circumstances, the amount of materials needed and the material costs in the budget based on construction drawings are lower than those in the construction budget. Answer: B
Reply #22015-11-06
It is known that project AF has two parallel background tasks, G and H. The latest start time for task G is day 12, while its earliest start time is day 8. The latest completion time for task H is day 14, and its earliest completion time is day 12. The time intervals between task F and tasks G and H are 4 days and 5 days respectively. Therefore, the total slack for task F is (c) days
Reply #32015-11-06
Regarding the construction budget, regarding the comparison between the construction drawing budget and the other type of budget, the correct answer is (b). The methods for comparing these two budgets include the physical comparison method
Reply #42015-11-06
17. C.7 18 B The methods for comparing “two calculations” include the physical comparison method
Reply #52015-11-07
B.5; A The preparation of the construction budget is based on budget quotas, while the preparation of the construction drawing budget is based on construction quotas
Reply #62015-11-07
17. It is known that project AF has two parallel background tasks, G and H. The latest start time for task G is day 12, while its earliest start time is day 8. The latest completion time for task H is day 14, and its earliest completion time is day 12. The time intervals between task F and tasks G and H are 4 days and 5 days respectively. Therefore, the total float for task F is (C) days: A. 0 B. 5 C. 7 D. 9. 18. Regarding construction budgets and the comparison between the budget based on construction drawings and other types of budgets, which statement is correct? (B) A. The construction budget is prepared using budget quotas, whereas the budget based on construction drawings is prepared using construction quotas. B. The methods for comparing these two types of budgets include a physical comparison method. C. In general, the amount of labor required and the labor costs in the budget based on construction drawings are lower than those in the construction budget. D. In general, the quantity of materials needed and the material costs in the budget based on construction drawings are lower than those in the construction budget
Reply #72015-11-10
17, C 18, B. . . . . . . . . .

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.