This post was last edited by Desert Fish on 2015-11-23 07:08. Let’s work on Question 79, Part 2: 65 multiple-choice questions from the 2015 First-Class Constructor Examination in Project Management. There are rewards for those who answer correctly. Those who do these questions every day are truly eager learners! ! Today marks the start of the project management series – welcome to join! *************************************************I have gathered some questions from this year’s first-level constructor exam, along with their answers. I’m sharing them here to increase everyone’s interest in participating. Instead of posting them all at once, I’ll present a few multiple-choice questions or one case study at a time, with the answers hidden. The answer will be visible after responding. Everyone is welcome to participate; those who give correct answers will receive a reward from the moderator. ****************************************** After completing the questions, it’s time to rest, and enjoying delicious food is the best way to do that. Everyone is encouraged to click on the posts related to food topics: a summary post of the “Food Search” series. Feel free to share your own ideas as well, and you’re also welcome to join discussions in the safety-related section. Fun posts about traffic violations – summary post. ****************************************** 65. Which of the following statements regarding the inspection of the thickness of the rebar protection layer is correct? A. The locations to be inspected are determined by the supervisor. B. For beams, 2% of the total number of components should be inspected, with a minimum of 5 components. C. For slabs, 5% of the total number of components should be inspected, with a minimum of 2 components. D. Non-destructive testing methods must be used. 【Standard answer】B
Regarding the statement on the inspection of the thickness of the rebar cover, the correct one is (b). B. For beams, 2% of the total number of components should be sampled, with a minimum of 5 components
65. Regarding the inspection of the thickness of the rebar cover, the correct statement is (B). A. The locations to be inspected are determined by the supervisor. B. For beams, 2% of the total number of components should be inspected, with a minimum of 5 components. C. For slabs, 5% of the total number of components should be inspected, with a minimum of 2 components. D. Non-destructive testing methods must be used
B. For beams, 2% of the total number of components should be sampled, with a minimum of 5 components
A. The location of the inspection site is determined by the supervisor
B. For beams, 2% of the total number of components should be sampled, with a minimum of 5 components
B. For beams, 2% of the total number of components should be sampled, with a minimum of 5 components