This post was last edited by hesonchang214 on 2016-7-24 10:04. Reward for participation: 2 Wealth. Reward for the correct answer: 9. When on-site supervision personnel carry out their supervisory duties, if they discover that the construction company is violating the mandatory standards for engineering construction, (  ).   A. Notify the professional supervision engineer immediately B. Notify the project owner immediately C. Has the authority to order corrections D. The chief supervision engineer shall order the construction company to make immediate corrections
Reply #22016-07-24
C. Has the authority to order rectification D. The chief supervision engineer shall order the construction company to carry out rectification immediately
Reply #32016-07-24
When on-site supervision personnel are carrying out their supervision duties and discover that the construction company is violating the mandatory standards for engineering construction, ( C ).  
Reply #42016-07-24
When on-site supervision personnel are carrying out their supervision duties and discover that the construction company is violating the mandatory standards for engineering construction, ( C ).   A. Notify the professional supervision engineer immediately B. Notify the project owner immediately C. Has the authority to order corrections D. The chief supervision engineer shall order the construction company to make immediate corrections
Reply #52016-07-24
When on-site supervision personnel are carrying out their supervisory duties, if they discover that the construction company is violating the mandatory standards for project construction, they have the authority to order the company to make immediate corrections; If it is found that the construction activities have already or may endanger the quality of the project, it shall be reported promptly to the supervision engineer or the chief supervision engineer, who will issue an order to suspend construction temporarily or take other emergency measures

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.