Safe fire separation distance between exhaust waste heat boiler and power distribution room

2016-12-05View Original

Thread Content

What is the appropriate safety and fire protection distance between a tar processing exhaust waste heat boiler and a power distribution room, and which standard should be followed? Thank you!
Reply #22016-12-06
In accordance with the requirements of GB50041-2008 \"Code for Design of Boiler Rooms\" and GB50016—2006 \"Code for Fire Protection Design of Buildings\": the distance between transformers in outdoor substation and distribution stations and factory buildings should be 12.0 meters for buildings with fire resistance ratings of 1 or 2, 15 meters for those with rating 3, and 20 meters for those with rating 4.
Reply #32016-12-07
Thank you! I would like to ask which category exhaust boilers fall under in the building codes!

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.