How to handle restarted projects

2017-06-29View Original

Thread Content

The original project has been restarted, and the drawings were completed before the new definitions for pressure pipes were established. Now that it’s restarted, do the technical documents such as the pipe data sheets need to be prepared again according to the new definitions? What is the relevant basis? If it isn’t changed, what impact will it have on subsequent installation and inspection?
Reply #22017-06-29
You need to ask the local special inspection agency; their opinion should be taken as the standard. Logically speaking, for the drawings that have already been delivered, those with a specified year in the standards should be followed according to the previous standards, while those without a specified year should be followed according to the latest standards.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.