During the initial commissioning purge of the device, should the safety valve on the container be removed? Or should the safety valve’s bypass line be used first during the purge, and then the safety valve itself be purged? Please share your opinions; extra points will be given
Before the initial startup purge, flow meters, control valves, throttling devices, safety valves, etc. should all be removed. They are reinstalled only after the pipeline purge test is successful. However, it is essential to prevent the equipment from experiencing overpressure during the purge process; a purge plan should be prepared along with appropriate safety measures before carrying out the purge.
Disconnect from the pipeline, use iron sheet as a separator in between; some also have safety valves that rest on the ground – it depends on the conditions on site~~~
The safety valve does not require purging; a bypass line is used. It is also necessary to consider whether the flare line is part of the cold wall or the hot wall system – if there is an excess in the cold wall bypass line, purging may not be necessary
During the initial startup, the safety valve must be removed; both target testing and pressure testing require pressures higher than the operating pressure to prevent the safety valve from activating, so as to meet the requirements of these tests
Before purging, remove the flange in front of the safety valve; reinstall the safety valve only after the purging is complete, otherwise impurities may be blown into the safety valve
The safety valve cannot be purged; it will only open when the set pressure is reached. After it returns to its original position, it needs to be recalibrated. It’s not clear whether this applies to weight-type valves as well.
The flange in front of the safety valve can be removed; it can be reinstalled after successful purging!
When we purge the safety valve, we purge its bypass line