HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

【Weekly Topic】【Civil Engineering Version 20170603】

2017-06-03View Original

Thread Content

Participation reward: 2 Wealth. Correct reward: 6 wealth. When using the value-engineering method for comprehensive analysis and control of costs and progress, the basic parameters that need to be calculated are ( ).   A. Actual cost of planned work B. Budgeted cost of planned work C. Actual cost of completed work D. Budgeted cost of completed work E. Actual cost of work to be completed Answer: B, C, D
Reply #22017-06-03
C. Actual cost of work completed D. Budgeted cost of work completed E. Actual cost of work to be completed
Reply #32017-06-03
When using the earned value method for comprehensive analysis and control of costs and schedule, the basic parameters that need to be calculated are (BCD).   A. Actual cost of planned work B. Budgeted cost of planned work C. Actual cost of completed work D. Budgeted cost of completed work E. Actual cost of work to be completed

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.