【Weekly Question】【Civil Engineering Version 20170716】
Thread Content
Participation reward: 2 Wealth. Correct reward: 6 wealth. Multiple-choice question. According to the provisions regarding joint bids in the \"Measures for Bidding on Construction Projects\", which of the following statements are incorrect? ( ) A. If a consortium passes the prequalification process, any changes in its composition must be approved by the tenderer before the deadline for submitting bids.B. The parties constituting the consortium must designate a lead member and submit to the tenderer a power of attorney signed by that lead member.
C. In the case of a consortium bid, the parties must designate a lead member and must submit the bid security in the name of that lead member.
D. In the case of a consortium bid, the parties must designate a lead member and authorize them to represent all consortium members in carrying out the tasks related to the bidding process and the implementation of the contract.
E. When a consortium submits a bid, the bid security submitted in the name of the lead member is binding on all members of the consortium.
Correct answers: B, C
B. The parties involved in a consortium must designate a lead member, and they must submit to the tenderer a letter of authorization signed by this lead member.
C. In the case of a consortium bid, the parties must appoint a lead member, who must also submit the bid security in the name of the consortium.
D. When bidding as a consortium, the parties must designate a lead member to act on behalf of all consortium members and to be responsible for oversight and coordination during both the bidding and contract implementation phases.
E. The bid security submitted in the name of the lead member within the consortium is binding on all members of the consortium
B. The parties involved in a consortium must designate a lead member, and they must submit to the tenderer a letter of authorization signed by this lead member.
C. In the case of a consortium bid, the parties must appoint a lead member, who must also submit the bid security in the name of the consortium.
D. When bidding as a consortium, the parties must designate a lead member to act on behalf of all consortium members and to be responsible for oversight and coordination during both the bidding and contract implementation phases.
E. The bid security submitted in the name of the lead member within the consortium is binding on all members of the consortium